admin

PROJECT COMPLETION

AIRA condominium has been successfully completed. All units have been sold out and the project is now closed.

Progress report for November 2018

Progress report for November 2018 – We have acquired a total of 27.41% overall progress percentage as of 30th of November 2018. Steel bars required for first floor and second floor were all delivered on site as well as the form-works materials such as plywood and hardwood. There were delays on some trades due to the late arrival of …

Progress report for November 2018 Read More »

Progress report for October 2018

Progress report for October 2018 – We have acquired a total of 26.24% overall progress percentage as of 31st of October 2018. Procurement for all the structural materials deliverables were carried out and we started procuring for the architectural and services materials. For the first floor level, a dedicated team were assigned to carry out reinforcement and shuttering …

Progress report for October 2018 Read More »

DEVELOPMENT PROGRESS

DEVELOPMENT PROGRESS – Mezanine floor slab casting in progress – Date: 28 June 2018.